I am a goal orientated leader determined to succeed in quality, safety, and performance. I have proficient skills with Navis works, I-Hawk, excel, and Microsoft. 19 years of experience in management & supervisory roles. I hold extensive knowledge in piping and mechanical systems while working on new construction, maintenance and shut down environments in sectors such as: oil & gas, pulp & paper, processing plants and mining. Skilled in planning and execution, coaching and mentoring a safety culture. I am currently looking to expand my career as a piping superintendent / general foreman, coordinator or planner. I hold a certificate in project management and currently am managing a team of 400+ pipefitters, millwrights and boilermakers at LNG Canada. One of my highlights of the project was planning and executing scope on underground water, drainage systems moving to above ground stick built, modular piping systems, and completing the gas inlet tie-in to the Coastal Gaslink pipeline in KITIMAT BC.

Overview

12
12
years of professional experience

Work History

Piping Superintendent / General Foreman

FLUOR CONSTRUCTORS FCCL - LNG Canada
08.2020 - Current
  • Aligning piping scope, factoring three-week / ninety -day look ahead to execute closing dates, complete project milestones
  • Managing planners for execution of deliverables
  • Use of ORG charts for management of teams
  • Underground installation of drainage and fire suppression / potable water systems GRE fiberglass, HDPE on 400 Hectares
  • Pipe installation all Alloys / pump strains / equipment installation
  • Materials Management
  • Manage RFI's, CQs, FCNS DR's
  • Progressing ongoing work to project controls
  • Supervise 400 plus pipefitters / welders
  • Interfacing with quality department/engineering and project managers
  • Directing and aligning scaffolders, electrical civil and millwrights
  • Reviewing permits and GDA's for scheduled and unscheduled work holding a supervisor ground disturbance ticket.

Steamfitter General Foreman

Ultimate Management Services - Kruger Pulp and Paper
05.2019 - 07.2020
  • Planning various routine outages and emergency shutdowns on equipment, vessels, heat exchangers, steam systems throughout the paper mill under tight schedules
  • Supervising hydro tests, creating testing plans, and setting test limits
  • Directing industrial radiographer / sub trades
  • Directing scaffolding contractor
  • Attending meetings with clients/engineers.

Steamfitter Foreman

PCL MELLOY: Parkland Refinery Shutdown Burnaby BC
02.2020 - 05.2020
  • Layout and piping verification of all spools before the demo of the unit
  • Replacement of various piping systems 2-16" including stainless, chrome, and carbon steel piping
  • Completing quality carbon steel x-ray fit ups for welders
  • Heavy rigging installing slide valves with chain falls and come along all throughout the cracker unit at different elevations.

Steamfitter Foreman

KEMANO Hydro Dam: Cascade Mechanical -Kitimat, BC
04.2018 - 09.2019
  • Demo/replacement of Generators 1 and 2 mechanical cooling piping
  • Stainless pipe fabrication all completed on-site
  • Supervising crew of 15 pipefitters/welders
  • Working with engineering contractors with RFI's
  • Reviewing isometric drawings, P&ID and schematics
  • Replacement of lube oil piping and exchangers
  • Replacement of air systems, valves, and vessels
  • Completed shutdown on storage tanks, replacing piping, valves, and repairing vessels assisting, recertification of vessels with radiography
  • Created safe work environment with zero injuries.

Steamfitter General Foreman

Lantic Sugar Refinery - RKM - Vancouver, BC
09.2018 - 02.2019
  • Supervisor 25+ pipefitters, millwrights, coaters, and Ironworkers installing new filter presses, and upgrading mechanical piping
  • Maintenance of steam systems installing valves, aligning pumps, and installing pressure vessels
  • Heavy Rigging using cranes to transfer filter presses and equipment into buildings / Working with engineering for heavy-lift plans
  • In charge of project procurement.

Steamfitter Foreman

PCL Constructors SUNCOR FORTHILLS - Alberta
04.2017 - 01.2018
  • Supervising Heavy lifts utilizing 300-ton cranes to install small to big-inch piping
  • Installation of big / medium bore 20,000LB - 30,000LB valves/actuators using beams to rig and transfer
  • Weld mapping and paperwork.

Steamfitter Lead Journeyman

Trotter and Morton Boiler-house University of British Columbia
09.2016 - 03.2017
  • New construction: installed 3 boilers for supply and return hot water heating piping systems
  • Installing equipment associated carbon piping, valves, and pumps
  • Reading blueprints, P&ID'S, and isometrics
  • Fitting x-ray quality welds

Steamfitter Foreman

BANTREL Constructors Kitimat Modernization - Kitimat, BC
02.2014 - 08.2016
  • New construction on Aluminum Smelter Modernization project at RIO TINTO
  • Supervising heavy lifts in Switchyard, installing transformers, turrets, cooling piping, and equipment.

Steamfitter Journeyman

CO-OP Upgrader Refinery, PCL Constructors - Regina SK
03.2012 - 02.2013
  • Working in Sat Gas / DEMIN unit installing mechanical piping, valves, and supports
  • Fab / Install carbon steel and stainless piping XRAY quality
  • Heavy lifts with cranes / Blind Lifts / Pipe and Equipment installation.

Education

Skills

Leadership - Superintendent - foreman 15 years experience

Supervising 400 pipefitters / boilermakers / Millwrights 4 years on biggest project in North America

Underground piping Systems (fire suppression HDPE / Fiber Glass / PVC drainage

New construction above ground / stick built / Pre- Fabrication (all ALLOYS) / Demo

Maintenance: Mechanical Systems / live plants

Planning / estimating - building and reviewing work packages

Communication / public speaking / Problem solving

References

  • Wayne Desranleau, General Piping & Iron Worker Superintendent, 780-246-2076
  • Tom Robb, Construction Manager/ Piping general Superintendent, 778-338-1950
  • Michael Koptyko, Piping Superintendent, 250-833-2260

Timeline

Piping Superintendent / General Foreman

FLUOR CONSTRUCTORS FCCL - LNG Canada
08.2020 - Current

Steamfitter Foreman

PCL MELLOY: Parkland Refinery Shutdown Burnaby BC
02.2020 - 05.2020

Steamfitter General Foreman

Ultimate Management Services - Kruger Pulp and Paper
05.2019 - 07.2020

Steamfitter General Foreman

Lantic Sugar Refinery - RKM - Vancouver, BC
09.2018 - 02.2019

Steamfitter Foreman

KEMANO Hydro Dam: Cascade Mechanical -Kitimat, BC
04.2018 - 09.2019

Steamfitter Foreman

PCL Constructors SUNCOR FORTHILLS - Alberta
04.2017 - 01.2018

Steamfitter Lead Journeyman

Trotter and Morton Boiler-house University of British Columbia
09.2016 - 03.2017

Steamfitter Foreman

BANTREL Constructors Kitimat Modernization - Kitimat, BC
02.2014 - 08.2016

Steamfitter Journeyman

CO-OP Upgrader Refinery, PCL Constructors - Regina SK
03.2012 - 02.2013