Over Five and a half years of experience in various heavy civil infrastructure projects in the execution department.
Experience includes a two-tier flyover (city infrastructure project), a major bridge over a canal (smart city project) and an airside infrastructure project at a metropolitan airport.
Handled billable clients throughout my previous experience.
Knowledge of Ontario Provincial Standard Specifications (OPSS).
Holds Construction Management: Safety & Health certificate.
Holds Class G Ontario driving license.
Overview
6
6
years of professional experience
Work History
Senior Engineer
LARSEN & TOUBRO CONSTRUCTIONS
08.2019 - 03.2022
PROJECT: NORTH-SOUTH PARALLEL RUNWAY PROJECT, BENGALURU INTERNATIONAL AIRPORT, KARNATAKA, INDIA
Promoted, led, and executed a safety-first culture for all employees, sub-contractors, and consultants in compliance with the project's environmental health and safety program
In charge of the excavation of the drain trench for a scope of about 10.7 km Concrete Trapezoidal Drain with Trimble Earthworks Automatics installed excavator, a Grade Control System
Ensuring drain alignment with the help of Trimble GPS Rover as per the drawing along with ensuring the provided FRL and Invert levels are maintained in the concrete lining
Kerb laying and Paver Block laying at an underpass tunnel and on the approach ramps
Supervised laying of APP-treated bituminous waterproofing membrane at the underpass tunnel and the approach ramps
Supervised approach slab constructions for the underpass tunnel approach ramps on either side including excavation, reinforcement, formwork and concreting
Preparation of material reconciliation on a monthly basis to ensure efficient usage and forecast future requirements and keeping a track record of work progress on a daily basis
Ensuring appropriate permits are issued for all the activities at the site such as Earthwork permits, Height work permits Night work permits and Airside work permits
Coordinated with clients for working methodology, and timely completion of the works and ensured the quality and specifications are followed as provided
Coordinated with project managers and subcontractors to ensure timely completion of activities within budget and schedule
Senior Engineer
Larsen & Toubro Construction
04.2019 - 08.2021
PROJECT: AMARAVATI SMART CITY PROJECT, ANDHRA PRADESH, INDIA
Periodically reassessing daily goals to meet forecasted production, schedules, and budgets
Handled the construction of RCC Foundations and Piers for a canal over-bridge and inspected subcontractors’ work
Executed and completed the excavation works involving about 40000 Cubic meters of hard strata soil on time and supervised the construction of two isolated sloped footings
BBS preparation for Isolated Sloped Footing and Pier and supervision of both steel and concrete works for the same
Prepared DPR (Daily Progress Report) using Procube as the project monitoring application
Kept track record of quantities of work done by the sub-contractors and prepared DLR (Daily Labor Reports)
Surveyed sites to determine material needs and accurately manage inventories and budgets
Coordinated with clients for working methodology, and timely completion of the works and ensured the quality and specifications are followed as provided
Coordinated with safety officials to maintain a safe workplace for workmen and machinery by updating
RTR (Reverse the Risk) status for every activity through an internal safety app and ensured permits from the client safety department are in hand for all the activities at the site.
Junior Engineer
KNR CONSTRUCTION LIMITED
06.2016 - 03.2019
PROJECT: TWO-TIER FLYOVER PROJECT, TAMIL NADU, INDIA
Supervised Pile cap, Isolated Shallow Pier foundation and Pier constructions along with BBS preparation for the same and fulfilled the expectations of clients and the Project Manager in terms of quality and timely completion for 60 Piers out of 164 along with foundation works
Worked in DMC (Direct Mud Circulation) method boring, chisel boring and auger boring for pile foundations and successfully completed 105 piles where all the tested working piles passed the Static Loading test
Monitored the quality of the works per the norms stipulated in the PQP and ensured the specifications followed as per the given drawings
Kept records of the quantity of work done by subcontractors
Managed site labour and equipment requirements and ensured the safety of the same
Handled the construction of the pier protection wall for about 5 km on both sides
Supervised soil testing (confirmatory boring test along with Standard Penetration Test) and maintained the bore log report.
Education
Ontario College Graduate Certificate - Construction Project Management