Develop skills in fast-paced, collaborative engineering environment, focusing on project scheduling and cost control.
Skilled in SAP, MOC, project management software, project schedule, budget and cost control, including conducting risk assessments, with keen eye for detail and accuracy.
Overview
34
34
years of professional experience
1
1
Certification
Work History
Project Controls Lead
JGIC
09.2024 - Current
Company Overview: JGIC(www.jgicadvidough.com) Calgary Canada
Project Controls Lead Sept2024-till date
Created and Updated Primavera Schedule
Performed risk analysis of project Schedule, using Primavera Monte Carlo Risk Analysis
Project Controls Turnaround
Black and Mcdonald Canada
11.2023 - 08.2024
Black& McDonald Calgary Canada March2024-June2024
Project Controls Turnaround, Plant49 Shut down Project CNRL Horizon Fort McMurray Alberta
Worked in10/4Fly in/Fly out camp rotation in Fort McMurray Alberta
Woking on shut down in Oil Industry
Project Controls Engineer
Imperial Oil Kearl Lake Project Fort Mcmurray Alberta Canada
06.2023 - 11.2023
Successfully completed64 Km pipeline system in Tailing area including2 No’s FTS (Fluid transfer system36 in dia) from Dredges to West Tailing Ponds,2 No’s30 in dia TSRU pipeline (Tailing solvent recovery units) and4 No’s28 in dia CST pipeline (coarse sand tailing) from Plant to ITA1 (In pit Tailing area1) Pond
System also included construction of12 in dia cold water pipelines,11 No’s4500 HP pumping stations,11 Electric houses,4 Substations,3 Dredges with associated marine structure,40 road crossings, Culverts, MSE (mechanically stabilised earthwork) and Slurry Walls1m wide,10m high,4km long)
Prepared progress reports for construction of Tailing area CST, TSRU, FTS pipelines and Pumping stations, Dredges, Pumping Stations, Subs stations, E-Houses, Slurry Walls
Verified LEMs
Prepared daily, weekly and monthly reports
Updated Primavera P6 Schedule on weekly basis
Prepared3,6 Weeks Look ahead
Prepared weekly presentation for progress presentations
Senior Planner/Scheduler
Clearbakk Water Solutions Calgary
09.2021 - 05.2023
Working on a $34 M , EPC Polymer Hydration Plant Project in Oil Industry Fort MacMurray Alberta
Prepared and implemented Project Controls Procedure
Developed schedule in P6, based on the budgeted hours and project scope of work
Prepared & issued2 &4 Weeks look Ahead to team for progress feedback, gave activity codes for filtration as per Responsible Engineers, Buildings & Disciplines for updating weekly progress feedback
Updated Schedule on Biweekly basis for client and weekly basis for internal review, Kept track of the budget man-hours & budget material quantities for comparison at different project stages
Developed and updated Progress report, Purchase orders status, RTS dates of equipment’s, Actual and Planned & Forecast progress on weekly basis
Attended Weekly meetings with Engineers, clients, and vendors for getting and updating progress information, Procurement, and construction teams daily to update daily information
Checked procurement log daily for information on issue of Purchase requisitions and PO’s and updated Their status in Primavera schedule
Claims & Forensic Planner-Independent Consultant
James and associates JGIC
05.2020 - 08.2021
Company Overview: James & Associates Calgary Canada
Performed Risk analysis of Project Schedules using Primavera Pert master Risk Analysis Software, Resource levelling to avoid any unexpected spike over the project life cycle
Prepared and implemented Project Controls Procedure, Prepared RFP Bid Schedules for Buildings, Bridges
Provided scheduling advisory services within the infrastructure, practice focused on project controls, project performance, commercial management
NYC Department of Design and Construction Awards Program
Management Contract for Borough-Based Jails
Claims & Forensic Planner-Independent Consultant
James & Associates Calgary
01.2017 - 11.2019
Performed construction scheduling and schedule analysis; EOT Extension of time Claims, project controls; earned-value management, project audits, reviews, construction claims
Performed Forensic analysis for Contractor’s Claims, Oil Industry Est cost $500 million projects claims, Est Cost Projects, $220 M,150 Km Gas pipeline project BC,50 cm32 Km Raw Water pipeline project, Slave Lake City, Cochrane Bridge H22x16 Interchange Improvements, AB, Water & Sewerage system Saprae Creek Fort Mc AB, Canada
Prepared and implemented Project Controls Procedure
Provided scheduling advisory services within the Infrastructure, practice focused on project controls, project performance, commercial management construction claims and disputes..Performed Risk analysis of Project Schedules using Primavera Risk Analysis Software
Analyzed and prepared construction schedules and perform forensic & Risk analysis
Performed Qualitative and quantitative risk analysis of project Schedules using Primavera
Set up WBS and activities, with relationships and activity codes
Communicated with Project managers, Construction managers & estimators
Provided guidelines to Design Team Leads and Design Planner for Design timeline set up
Contributed in preparation of proposal documents for SWCRR Project Calgary, Master Schedule Simplified Timeline Schedule, and detailed Construction Schedule
Set up construction activities timeline in compliance with Canadian & Alberta Environmental regulations
EPC Project, Two Central Processing Facilities (est
Cost $2.6 Billion) Husky Sunrise SAGD, Fort Mcmurray Alberta, Canada,2
EPC Hydro-Treaters (est
Cost, $480M), CNRL Plant in Fort Mcmurray, AB Canada,3
Piling, Water disposal and Firewater system in Vacuum Distillation & Distillation Recovery Units, Tailing Pipeline, Industrial sewage system, Temporary Facilities,Installation of Diesel Turbines and200 Mega Watt4 Generators of Power Plant at Husky Plant
Prepared and implemented Project Controls Procedure
Developed schedule in P6, based on the budgeted hours and project scope of work
Updated Schedule on monthly basis, Kept track of the budget man-hours & budget material quantities for comparison at different project stages
Resource levelled to avoid any unexpected spike over the project life cycle
Developed schedule in P6, based on the budgeted hours, drawings and project scope of work and linked logically with the work sequence, target and imposed or constraint dates
Resource loaded with labor resources - per trade/ material resources/loaded with equipment resources and attach to the proper Calendar
Reviewed Critical path on weekly basis and compared critical activities to the Project base line.Performed Risk analysis of Project Schedules using Primavera Risk Analysis Software
Developed & Maintained Project Control Report such as S Curve, Commodity Curve, Multi Discipline Productivity Curve & Schedule Log manpower Histogram and progress and productivity report
Performed project planning and development of multi-level, resource loaded schedule
Prepared and implemented Project Controls Procedure
Maintained cost budgets and cost forecasts utilizing a change management system
Reviewed the completed schedule and got approved by project team and the client, assigned baseline of the project
Reviewed Critical path on weekly basis
Compare critical activities to the Project base line to be sure that the required correction action is been taken to bring the schedule back on schedule or to deal with any delay in completion.Performed Risk analysis of Project Schedules using Primavera Risk Analysis Software
Updated project schedule with actual man-hours used
Forecasted ETC man-hours, labor, and non-labor resource loading
Project Controls Engineer
Suncor Energy Canada
01.2007 - 07.2008
Was accountable for coordinating effective cost control processes, standards, systems to enable Downstream EPC projects, program and portfolio management of27 EPC projects (est
Cost $500Million) in Tailing, Extraction Plant Utilities& Facilities, including a30” dia,25 KM Tailing Ponds Pipeline Project (est
Cost $200 Million) in Sustainable projects department
Coordinated the preparation, consolidation, and analysis of project reports
Worked on Project systems and Plant maintenance module of SAP-R/3.Provided guidance to project management on matters relating to project controls
Compared actual, planned, and forecast hours, costs, and explained variances
Prepared & updated schedules in Primavera P6, MS Project and Plant maintenance in SAP-R/3.Performed Risk analysis of Project Schedules using Primavera Risk Analysis Software
Maintained cost budgets and cost forecasts utilizing a change management system
Chand Bagh School Development Project (Estimated cost Rs.210 millions) Project Manager/ Engineer (Civil)
Performed quality control and safety, Contract administration of Buildings and Infrastructure
A& C Construction Saudi Arabia (Jan1997-Dec1999) FFHP Housing Project Kharaj Riyadh (estimated cost S.R1350 millions) Senior Field Engineer (Civil)
Performed quality control and, Contract administration of Buildings, Roads, Civil Infrastructure
Installation of4 Diesel Turbines and Generators of200 MW Power Plant
Premier Consultants Pakistan (Jan1991-Dec1996) Planner/Site Engineer/Project Manager (Civil)
Performed estimation, quality control, Contract administration on Buildings &Civil infrastructure
Worked on Installation of Generators and Turbines on Ghazi Botha1750 MW Hydroelectric Power generation Plant
Trainings
Education
Master of Engineering - construction management in construction management
Concordia University Montreal
Montréal, QC
01.2006
Bachelor's Degree - BSc. Civil Engineering
University of Engineering & Technology Lahore Pakistan
Lahore, Punjab
12.1990
Skills
MS project- SAP (Project systems and Plant Maintenance Module), Primavera, Advanced Level of MS Office
Excel, Power Point and Outlook Effective presentation & Communication, Project management, Planning and Cost Control Analytical and Problem solving, process streamlining
Budgeting
Strategic Planning
Project Management
Presentation Skills
Change Management
Business Development
Process Improvement
ERP Systems
Project Engineering
Microsoft Project
Certification
PMP
February2017 to Present
Personal Details
Highest Level of Education: Master's Degree
Total years of experience:30
Links
https://www.linkedin.com/in/wasimsbhatti
Timeline
Project Controls Lead
JGIC
09.2024 - Current
Project Controls Turnaround
Black and Mcdonald Canada
11.2023 - 08.2024
Project Controls Engineer
Imperial Oil Kearl Lake Project Fort Mcmurray Alberta Canada
University of Engineering & Technology Lahore Pakistan
Master of Engineering - construction management in construction management