Strategic Senior Projects Manager with 20 years’ experience in the construction business acquired through several major projects in different sectors of activities such as Energy, Rail Transit, Building, Infrastructure and Petrochemical.
Expert in Construction Project Management, Contract Administration, Project Engineering, Design Management, Project Integration and Risk Mitigations.
Constantly committed to customer’s satisfaction and accountable for all aspects of project delivery, budgets, and contractual milestones.
Motivating and inspiring leadership with excellent communication skills.
Project: REM – Réseau Express Métropolitain (Execution Phase)
Client: CDPQ
Engaged during 5 years in the construction of this mega LRT project of 64 KM of track in the great area of Montreal city (Canada), I have:
Project: Trillium LRT (Proposal Phase)
Client: Ottawa City
Responsible to conduct the proposal effort to evaluate an estimate for the construction of MEP systems of the train stations, I have:
Project: REM – Réseau Express Métropolitain (Proposal Phase)
Client: CDPQ
Having participated in the proposal of this project, I was involved in the engineering coordination, estimation, and procurement efforts of the LRT systems scope of work. My main responsibilities were :
Project: PSC MSF Center (Proposal & Execution Phases)
Client: Agence Métrpolitaine de Transport (AMT)
Having taken responsibility of this fixed-price contract for the supply and installation of an overhead catenary system (OCS) for the train maintenance and storage facility in the city of Montreal, I managed different scopes among several project phases including the following :
Accomplishments :
Project: Cochrane & Long Lake Solar Farms (Execution Phase)
Client: Northland Power
Awarded as a T&M contract to build 4 solar panel fields in the city of Cochrane in northern Ontario. Responsible of contract administration and project scope management, I have:
Project: Nitrogen fertilizer production plant (Proposal Phase)
Client: IFFCO Canada
During this project I led the estimation process to produce a budget estimate of the electrical/instrumentation portion of the proposed fertilizer plant project at the Bécancour industrial complex in Quebec City. Among other responsibilities, I have:
Project: Lower Mattagami River (Proposal & Execution Phases)
Client: Ontario Power Generation (OPG)
This EPC contract was for the engineering, procurement and construction of a new hydroelectric plant and the extension of three others existing power stations. My role was to assist the construction manager in the organization and management of the electrical department. I have:
Project: New production unit– Client: Dow Chemical
Project: Completion of the Highway 30 – Client: MTQ
Project: Cogeneration Plant – Client: Northland Power
Project: Nickel processing center – Client: VBNC
Project: Montreal/Laval Subway Extension – Client: AMT
(Proposal & Execution Phases)
Having participated to the different projects listed her above, I took care of the projects control processes. More in detail, I have:
English, French, Arabic
PMP - Project Management Professional
Temporary Engineering & Technical Risks - 2017, Omaha, USA
Overhead Contact System & Traction Power 2017, Toronto, Canada
Preparation of PMI Exam Seminar - 2015, Montréal, Canada
Act as a Leader - 2014, Montreal, Canada
Design Integration in EPC projects - 2014, Omaha, USA
Lead Estimating - 2014, Omaha, USA
Operation Management, 2013, Omaha, USA
QA/QC Academy Course, 2012, Steamboat, USA
Scheduling Academy Course, 2012, Denver, USA
Construction of Mechanical Systems - 2010, Omaha, USA
Project Engineering - 2009, Montreal, Canada