I am a Business Consultant/Engineer experienced in facility design optimization, asset management, logistics, safety, training, operations, change management & operational readiness. I am skilled in strategy development, risk management, process development & modeling, engineering & project control toolsets, team selection, assembly & training, construction, commissioning & startup. I have a proven Track record in Mining & Electrical Utilities.

Overview

33
33
years of professional experience

Work History

Envirogold
01.2025 - 07.2025
  • Responsible for directing test work proving the efficacy of preconcentration of old tailings, prior to application of a patented leach process to extract residue metal values & eliminate the potential for acid water generation.
  • Responsible for directing the development of a virtual operation based on this test work.

Spanish Mountain Gold
05.2023 - 07.2024
  • Responsible for process development test work including coarse ore flotation.
  • Responsible for development of a virtual plant during prefeasibility to optimize process equipment specification demonstrating a 25 % energy reduction through an integrated process & electrical simulation encapsulated in a project management estimating system.
  • Worked with various suppliers to estimate CAPEX & OPEX based on a tagged process & electrical equipment list as part of a the PFS.
  • The work resulted in developing an electrical load & distribution system approved & funded by the electrical utility.

Project Management Consultant

McEwen Mining Los Azules
05.2021 - 02.2022
  • Introduced key personnel responsible for completing the access road.
  • Lead the development of the process plant simulation.
  • Introduced an advanced project management system that managed drilling & drill core assays & warehousing.

Project Management Office Consultant

Los Calatos Holdings (LCH)
05.2017 - 12.2018
  • Worked closely with CD capital Joint Program Offices to deliver timely outcomes for the business.
  • Fostered a “can do” work culture.
  • Designed & implemented a program office for the LCH Project that is scalable to manage multiple projects.
  • Provided support to the Technical Program Manager through the provision of all back-office operations to enable the efficient delivery of the PFS/FS.
  • Developed & Managed the Detailed Project Gantt including (but not limited to) key deliverables, interdependencies, timelines, resources, costs, risks & contingencies.
  • Developed & Implemented Controls to ensure all probity, integrity & transparency.
  • Developed & implemented monthly management reports.
  • Developed & implemented best practice processes & procedures for the Program Office.
  • Created Corporate Presentations, Board Papers & or similar as required.
  • Analyzed the business to determine the existing support processes & develop best of breed solutions to support the efficient operations of the Company from Feasibility Study through to Production.
  • Developed Timely Budgets Versus Actual Reports.
  • Managed the audit process at a parent & subsidiary level.
  • Managed Vendors from Tender through to delivery & ensure tight fiscal & time controls.
  • Managed the daily operations of all support functions & define the strategic direction for same including Risk Management, Finance, Legal, Procurement, Logistics, Information Technology, HR, Security, QA/QC, Community Relations & Government Relations.
  • Fostered “Risk Management” as a culture.
  • Developed an IT platform to support the global nature of business.
  • Undertook performance reviews for all staff & staff.
  • Developed the Company’s Anti-Bribery & Anti-corruption Policies consistent with the UK Bribery Act 2010 & implemented controls to manage these risks.
  • Provided Technical Support where required including.
  • Development of an approach to develop this unique vertical deposit.
  • Lead the development of a virtual plant.
  • Development of saltwater supply & treatment requirements.
  • Assisted the Company through leveraging personal networks to attract & retain the best Talent.
  • Fostered a strong Team based culture, where communication is open, honest & non-threatening.
  • Peru

Project Consultant

AZ Mining
01.2016 - 05.2017
  • Responsible on this Pb-Zn project.
  • Setup Project Simulation & Project Systems.
  • Supported Feasibility Project Management.
  • Developed the Plan for Operational Readiness.
  • Tucson, Arizona

Project Consultant

HUDBAY MINERALS
02.2015 - 01.2016
  • Developing project stage gate checklist.
  • Detailing project information requirements for vendors, engineers & logistics providers to support operational Readiness.
  • Rosemont Copper Molybdenum Project, Tucson, Arizona

Project Consultant

HUDBAY MINERALS
09.2012 - 02.2015
  • Project Information Systems including ERP (SAP) & Plant Historian selection & Site networks including WIFI.
  • Project Data & Document management to support Business Readiness.
  • Supporting Site logistics utilizing QR codes & handheld devices.
  • Site access control & construction camp utilization.
  • Justification & application of the process simulator for training, regulatory & advanced control checkout & plant debottlenecking.
  • Plant capacity verification linking the block schedule to the process model for the first 18 months.
  • Selection of Computer Based Training (CPT).
  • Verified plant cable lists & associated electrical design.
  • Constancia Copper Molybdenum Project, Cusco, Peru

Project Consultant as Project Director

MICRON RESOURCES CORPORATION
11.2010 - 08.2012
  • Implementing GIS for site delineation of historical exploration results for this 180 square mile Gold & REE prospect.
  • Completed Scoping Study.
  • Planned & managed the property drilling program.
  • Selected & implemented the mine planning system (Mincom).
  • Lead the process development program including the design of the drill sample preparation laboratory, ferromagnetic & paramagnetic separation testing facilities for magnetite recovery.
  • Redesigned the Gold & Magnetite pilot plant.
  • Selected project consultants & completed the Prefeasibility Study.
  • Bowie, AZ

Project Consultant

NEWMONT MINING CORPORATION
11.2008 - 10.2010
  • Defining core business processes to support capital effectiveness & delivery of business ready facilities.
  • Developing & documenting project standards required to support these processes including project definition, design & construction including transition from the EPCM teams to the operations & maintenance start-up teams.
  • Detailing the technology framework requirements to support these business processes including Newmont Corporate & Project Systems as well as EPCM & Vendors Systems.
  • Defining budgets & resources required to execute these standards & processes on both large & small capital projects including development of the overall execution plan & schedule for project teams.
  • Justifying the use of a dynamic simulator for the Conga Project to improve both process & process control design & operator training.
  • Completing “Business Readiness Requirements” for both Akyem (Ghana) & Hope Bay (Canada).
  • Denver, CO

Project Consultant

FREEPORT MCMORAN
12.2007 - 10.2008
  • Drafting the corporate capital projects standard operating procedures & contract terms to support business readiness for major projects including:
  • Climax 2010, Colorado.
  • Safford Sulfur Burner, Arizona.
  • El Abra Sulfolix, Chile.
  • Bagdad Molybdenum Conversion, Arizona.
  • Bisbee Feasibility Study, Arizona.
  • Cerro Verde II (Expansion), Peru.
  • Interfacing with EPCM’s including Fluor, Jacobs, & Aker Solutions to execute projects according to these SOP’s.
  • Phoenix, AZ

Project Consultant

PHELPS DODGE INC
01.2005 - 05.2007
  • Development of the associated contract requirements, overall business processes & standards for the EPCM, Suppliers, Commissioning Agents & for the provision of the data & documents required for on-going operations, including asset & supply chain management.
  • Directing the development of an (EPISTLE) ISO based web site for the assembly & quality assurance of data & documents from the Owner, Engineer, Suppliers & Commissioning Agents.
  • Managing the ERP System configuration & the upload of the required data & documents supplied prior to commissioning.
  • Detailing the assessment process for the determination of the required capital spare parts & components.
  • Justifying the use of a dynamic simulator for design verification, DCS checkout & operator training.
  • Integrating competency-based training program for both operations & maintenance incorporating hardcopy manuals, classroom training, computer-based training modules & dynamic simulation system.
  • Reviewing construction risk dossiers & filing the information into the document management.
  • Cerro Verde, Arequipa, Peru

Project Consultant

PLACER DOME INC
04.2004 - 12.2004
  • Justifying & designing the use of the SAP production planning (PP) for global deployment at Placer Dome, piloted at the Red Lake, Ontario underground gold mine.
  • Specifying the overall application architecture to ensure delivery of the required gold production through the integration of mine planning with SAP production planning system.
  • Detailing assets & their categorization from project, financial, maintenance & production perspectives.
  • Focusing on production & maintenance reporting to ensure effective project & production cost management.
  • Vancouver, BC

Director

AMEC ENGINEERING & CONSTRUCTION SERVICES
10.2001 - 03.2004
  • Strategy, marketing, sales, & management of the Operations & Maintenance Consulting Practice for the Americas.
  • Key Projects included:
  • Development of a risk-based program for the restart of the Falconbridge’s Kidd Creek Plant.
  • Risk assessment for the BC Hydrothermal Power Plant.
  • Information standards & requirements to support optimized design, construction, operations & asset management at BP’s new world-class SECCO Chemical Complex in China.
  • Business Plan, staffing & facilities selection for a new warehouse/ cross-dock for Kennecott Utah Copper to support their maintenance inventory reduction program (in partnership with Ausenco).
  • Developing corporate project information requirements, based on ISO, for Phelps Dodge Corporation.
  • Bellingham, WA

Manager Systems Planning

BC HYDRO
01.1993 - 01.1995
  • Developing the system strategic plan to improve ROI on the $100 million in annual information systems expenditures.
  • Specifying corporate guidelines & procedures for system specification, justification & implementation.
  • Working with Steven Spewak to develop enterprise data, technology & application architectures.
  • Re-engineering the roles of two hundred computer development & operations staff.
  • Detailing $100 million transmission & distribution systems upgrades to improve flexibility, accessibility & customer service.
  • Introducing real-time monitoring for large industrial customers, improving service & reducing costs.
  • Completing the business plan to upgrade the firm's $30 million investment in AM/FM/GIS to re-engineer the use of spatial data & improve asset management.
  • Demonstrating real-time Geographic Information Systems for transmission & distribution situation monitoring.
  • Vancouver, BC

Education

MBA degree - Finance & Management Information Systems

UBC

Undergraduate Degree - Mining & Mineral Processing Engineering

UBC

Engineering Thesis - Newmont Similkameen Mine’s SAG Grinding Circuit Modeling

MBA Thesis - Planned Maintenance Management Systems at Noranda

Certificate - Advanced Control

University of Alberta

Certificate - Maintenance Planning

Phelps Dodge

Knowledgeable in ERP Systems including SAP

Skills

  • Project management systems
  • Digital twin creation
  • Stage gate
  • Asset management

Timeline

Envirogold
01.2025 - 07.2025

Spanish Mountain Gold
05.2023 - 07.2024

Project Management Consultant

McEwen Mining Los Azules
05.2021 - 02.2022

Project Management Office Consultant

Los Calatos Holdings (LCH)
05.2017 - 12.2018

Project Consultant

AZ Mining
01.2016 - 05.2017

Project Consultant

HUDBAY MINERALS
02.2015 - 01.2016

Project Consultant

HUDBAY MINERALS
09.2012 - 02.2015

Project Consultant as Project Director

MICRON RESOURCES CORPORATION
11.2010 - 08.2012

Project Consultant

NEWMONT MINING CORPORATION
11.2008 - 10.2010

Project Consultant

FREEPORT MCMORAN
12.2007 - 10.2008

Project Consultant

PHELPS DODGE INC
01.2005 - 05.2007

Project Consultant

PLACER DOME INC
04.2004 - 12.2004

Director

AMEC ENGINEERING & CONSTRUCTION SERVICES
10.2001 - 03.2004

Manager Systems Planning

BC HYDRO
01.1993 - 01.1995

MBA degree - Finance & Management Information Systems

UBC

Undergraduate Degree - Mining & Mineral Processing Engineering

UBC

Engineering Thesis - Newmont Similkameen Mine’s SAG Grinding Circuit Modeling

MBA Thesis - Planned Maintenance Management Systems at Noranda

Certificate - Advanced Control

University of Alberta

Certificate - Maintenance Planning

Phelps Dodge

Knowledgeable in ERP Systems including SAP

Work Preference

Job Search Status

Open to work
Desired start date: Flexible

Desired Job Title

Project Management ConsultantProject Management Office ConsultantProject Consultant

Work Type

Full TimeContract Work

Important To Me

Stock Options / Equity / Profit SharingTeam Building / Company Retreats

Accomplishments

Black Belt taekwondo

Search and Rescue Trainee

Affiliations

  • Sigma Phi Delta
  • Canadian Legion